| S.No. |
Name of project |
Capacity (in MWs) |
Peaking Capacity (duration)/ Base load plant |
Expected commissioning |
Likely off-takers |
Date of signing MoU / PPA |
| 1 |
SMEC West Seti Hydro Electric Corp. Ltd. for West Seti HEP |
750 |
Peaking Cap. - 8 hrs |
2009 |
Punjab / Haryana / Rajasthan / Delhi |
21.10.2003 |
| 2 |
Meenakshi Power Ltd. For Middle Kolab and Lower Kolab Small Hydro Electric Project |
37 |
Peaking Cap. nil |
2007 |
West Bengal |
06.01.2004 |
| 3 |
Lanco Amarkantak Power Pvt. Ltd. Korba Thermal Power Plant |
300 |
Base Load Plant |
2008 |
MP |
24.05.2004 |
| 4 |
Orissa Power Consortium Ltd. For Samal HEP |
20 |
Peaking Cap. - 3 hrs |
2007 |
Bihar / Jharkhand / West Bengal |
22.03.2004 |
| 5 |
Everest Power Pvt. Ltd. for Malana-II HEP in Himachal Pradesh |
100 |
Peaking Cap. - 4 hrs |
2007 |
Punjab / Haryana |
09.03.2004 |
| 6 |
Maithon Power Ltd. For Maithon Right Bank Thermal Power Project |
1000 |
Base Load Plant |
2009-10 |
States of NR |
12.12.2002 |
| 7 |
Vemagiri Power Generation Ltd. for Gas Based Project in East Godavari, AP [Ph-II] |
740 |
Base Load Plant |
2008 |
States of SR |
28.03.2003 |
| 8 |
Jaypee Karcham Hydro Corp. Ltd. for Karcham Wangtoo HEP in Himachal Pradesh |
1000 |
Peaking Cap. 4 hrs |
2009 |
Punjab / Haryana / Rajasthan / Delhi |
18.06.2003 |
| 9 |
Chennai Power Generation Ltd. For Thermal Power Project in T.N. |
1000 |
Base Load Plant |
2008 |
States of SR |
10.12.2003 |
| 10 |
Swasti Power Engg. Ltd. for Small HEP at Ghanshali in Uttaranchal |
22.5 |
Peaking Cap. |
2006 |
Punjab / Haryana / Rajasthan |
23.12.2003 |
| 11 |
Sidheswari Power Generation Pvt. Ltd. Small HEP in Orissa |
10 |
Peaking Cap. |
2006 |
Bihar / Jharkhand |
01.01.2004 |
| 12 |
Torrent Power Generation Ltd. For LNG/ Gas based project in Gujarat |
270 |
Base Load Plant |
2008 |
MP / Maharastra |
13.01.2004 |
| 13 |
Vadinar Power Company Ltd. [ESSAR] for In-house Refinery Residue based Project in Jamnagar, Gujarat |
1200 |
Base Load Plant |
2006 |
MP / Gujarat / Maharashtra |
22.01.2004 |
| 14 |
Aban Loyd Chiles Off-shore Ltd. For Gas Based Project in Haryana |
260 |
Base Load Plant |
2007 |
Punjab / Haryana / Rajasthan |
25.03.2004 |
| 15 |
NEEPCO for Kameng HEP in Arunachal Pradesh |
600 |
Peaking Cap. |
2009-10 |
NER / Other Regions |
13.04.2004 |
| 16 |
NEEPCO for Natural Gas based CCP Plant in Tripura |
280 |
Base Load Plant |
2006-07 |
NER/ Other Regions |
13.04.2004 |
| 17 |
Suma Powergen Pvt. Ltd. for Gas based Power Project in Agartala, Tripura |
60 |
Base Load Plant |
2006-07 |
NER States |
04.06.2004 |
| 18 |
Sharvani Energy Pvt. Ltd. for Small HEP in Orissa |
12 |
Peaking Cap. |
2006-07 |
West Bengal |
07.06.2004 |
| 19 |
KVK Nilachal Pvt. Ltd. for Thermal Power Project in Vishakapatnam, A.P. |
250 |
Base Load Plant |
2007 |
Kerala / TN / Karnataka |
15.07.2004 |
| 20 |
ONGC for Various projects in the Country |
3000 |
Base Load Plant |
------ |
|
28.07.2004 |
| 21 |
Essar Power Ltd. for Gas based Power Project in Hazira, Gujarat. |
1500 |
Base Load Plant |
2008 |
States of WR |
19.08.2004 |
| 22 |
India Power Corporation Ltd for Coal based Plant in Orissa |
100 |
Base Load Plant |
2007 |
NR / WR States |
27.10.2004 |
| 23 |
Lanco Green Power Private Ltd. For Budhil HEP in Himachal Pradesh |
70 |
Peaking Cap. 4 hrs |
2008 |
States of NR |
03.11.2004 |
| 24 |
Jindal Power Ltd. For
Coal based Thermal Power Project in Chattisgarh |
300 |
Base Load Plant |
2008 |
Gujarat |
11.11.2004 |
| 25 |
India Power Projects Ltd. For Natural Gas based Power Project in Tamil Nadu |
1873 |
Base Load Plant |
2009 |
States of SR |
31.12.2004 |
| 26 |
Gujarat Paguthan Energy Corporation for Combined Cycle Gas Project in Gujarat |
700 |
Base Load Plant |
2008 |
States of WR / Rajasthan |
07.03.2005 |
| 27 |
Gujarat State Energy Generation Ltd. For Combined Cycle Gas Project in Gujarat |
595 |
Base Load Plant |
2009 |
States of WR / Rajasthan |
04.03.2005 |
| |
Total |
16049.5 |
|
|
|
|
| S.No. |
Name of project |
Capacity (in MWs) |
Peaking Capacity / Base load plant |
Expected Date of commissioning |
| 1 |
JKPDCL for Baglihar HEP in J&K |
450 |
Peaking Cap. 5-6 hrs |
2006 |
| 2 |
Damodar Valley Corporation for Mejia Thermal Project in Jharkhand |
500 |
Base Load Plant |
2006 |
| 3 |
Rolep Hydro Electric Power Company Ltd. For Rolep HEP in Sikkim |
36 |
Peaking Cap. |
2008 |
| 4 |
Him Urja Private Ltd. For Vanala HEP in Uttaranchal |
15 |
Peaking Cap. |
2008 |
| 5 |
Him Urja Private Ltd. For Dewali HEP in Uttaranchal |
13 |
Peaking Cap. |
2008 |
| 6 |
Karnataka Power Corporation Ltd. For Coal based Thermal Power Project in Bellary, Karnataka |
260 |
Base Load Plant |
2009 |
| |
Total |
1274 |
|
|